This commercial renovation project for a local
museum whose existing exhibit space had not be
remodeled in about ten years. We worked very closely with
an Architect from Ohio and an exhibit manufactuer from
Louisianna to insure that the renovated exhibit space would house the
new exhibits smoothly. The timeline allowed for this project
was only three months long, which included producing some CAD drawings,
securing permits, and the total gut and renovation of the space. The
museum had publicized the grand opening date prior to awarding the
project and the three month timeline was very critical to
maintain. One mistake could have cost the client thousands of dollars.
|